If you set the status of a job as Started or Completed, you can automatically set the status of previous work within the same order to Completed. Set one of the following settings to enable recursive results.

  • Check the "Result recursive flag" of the project.
  • Check the "Result recursive flag" of the operation.
  • Set the "Result recursive flag" of the results table to 1 and import it.

In addition, the method of reflecting the recursive results can be changed according to the settings of the project property "How to reflect the recurrence results flag" (Spec change tab). Note that this property requires a Ver. 16.0 license. If you don't have a Ver. 16.0 license, the behaviour is the same as "Not based on time constraint method".

How to reflect the result recursive flag

do not consider the time constraint method

Time constraint method of the previous process operation will not be considered. The process will only be completed when all of the work following the previous process operation is completed.

do consider the time constraint method

Time constraint method of the previous process operation will be considered.

  • In the case of ES, the status will be Completed when one of the following process operations has been Started or Completed.
  • In the case of SS, SSEE, EES, and ESSEE, the status will be set to Started when one of the following process operations has been Started or Completed.
  • In the case of ESE and SSEEE, if the operation in your process is split, the status will not be changed even if the following process operation becomes Started. This is because it is not uniquely determined which subdivision operation status should be changed.

Hinweise

  • Even if operations in the previous processes have their results specified , the recursive process will still be performed for the operations. When the status is "Completed", the "Results obtain time" will be cleared. When the status is "Started", the "Results obtain time" and "Reported qty" will be cleared.
  • Even if the result recursive property is unchecked, the status and the result recursive property of the previous process operations will remain unchanged.
  • The status of the previous operation will be changed recursively. If the operation is split, the status of the previous operation is changed recursively for each split operation. For details, please click here.